Gimboki Water treatment works

  • Home
  • -
  • Gimboki Water treatment works

Gimboki Water treatment works

energy December 19, 2025 0 Comments

The new 1MVA transformer was installed and energised. 2.2km of 33 kv line was constructed. 300m of 11kV cables installed. The objective of improving the reliability of supply to the sewer treatment by increasing capacity was met

Tags:

Share:

Leave Comment